*July 30th - August 4th* This is the City of Pittsburgh's 2018 paving season one week look ahead. This includes the name of the street followed by two cross streets, this section of street in between those two intersections is where resurfacing work will take place. Usually this work will consist of one day of Milling, or removing the existing asphalt, followed soon after by another day of Paving. *Weather and other factors may change the dates listed below.* Please check for posted signs on your street and follow us on twitter @PghDOMI <https://twitter.com/pghdomi> for updates. Street work may be rescheduled to a different day this week or added to a future week's schedule. Please share this information and any updates with your tenants and neighbors. *Woodward Avenue* Stetson Street to Dead End Milling: 07/30 Paving: TBD *South Twenty Fourth Street* East Carson Street to Sarah Street Milling: Complete Paving: 07/30 *Larkins Way* South Eighteenth Street to South Seventeenth Street Milling: Complete Paving: 07/30 *Harcum Way* South Seventeenth Street to South Twentieth Street Milling: Complete Paving: 07/30 *Clinton Street* South Fifteenth Street to Dead End Milling: Complete Paving: 07/30 *Tyndall Street* Lanpark Street to Allendale Street Milling: Complete Paving: 07/30 *Universal Street* Tyndall Street to Chetopa Street Milling: Complete Paving: 07/30 *Newcomer Street (Vidette)* Mutual Street to Kelvin Street Milling: Complete Paving: 07/30 *Kelvin Street* Newcomer Street to Tybee Street Milling: Complete Paving: 07/30 *Fire Way* Dead End to Dead End Milling: Complete Paving: 07/30 *Walton Avenue* Overview Street to Midwood Avenue Milling: 07/31 Paving: TBD *Well Street* Plymouth Street to Sweetbriar Street Milling: 07/31 Paving: *Mount Joseph Street* Thielman Avenue Newett Street Milling: 07/31 Paving: *Brushton Avenue* Baxter Street to Hamilton Avenue Milling: Completed Paving: 07/31 *Bower Street* Hyatt Street to Pointview Street Milling: Completed Paving: 07/31 *Fire Way* Dead End to Dead End Milling: Complete Paving: 07/31 *Universal Street* Tyndall Street to Chetopa Street Milling: Complete Paving: 07/31 *Tyndall Street* Lanpark Street to Allendale Street Milling: Complete Paving: 07/31 *Ashtola Way* Allendale Street to Dead End Milling: Complete Paving: 07/31 *Tyndall Street* Lanpark Street to Allendale Street Milling: Complete Paving: 07/31 *Stafford Street* Minton Street to Hammond Street Milling: Complete Paving: 07/31 *Federal Street* Lafayette Street to Perrysville Avenue Milling: 08/01 Paving: 08/02 *Brim Way* Reddour Street to Arch Street Milling: 08/01 Paving: 08/02 *Mulberry Way* Nineteenth Street to Twenty First Street Milling: 08/01 Paving: 08/02 *Spring Street* Devlin Street to Dengler Street Milling: Complete Paving: 08/01 *Syrian Street* Spring Street to Azul Street Milling: Complete Paving: 08/01 *Parkwood Road* Eisel Street to 920 Address Milling: Complete Paving: 08/01 *Moyer Street* Allendale Street to Francisco Street Milling: Complete Paving: 08/01 *Bergman Street* Hammond Street to Narcissus Ave Milling: Complete Paving: 08/01 *Wittman Street* Westchester Street to Winona Street Milling: Complete Paving: 08/01 *Centre Ave* North Craig Street to South Aiken Avenue Milling: Complete Paving: 08/02-03 *North Neville Avenue* Centre Avenue to Fifth Avenue Milling: Complete Paving: 08/02-03 *Springfield Street* Crest Way to New York Street Milling: Complete Paving: 08/02 *Hestor Drive* Hamburg Street to Springfield Street Milling: Complete Paving: 08/02 *Crest Way* Springfield Street to Dead End Milling: Complete Paving: 08/02 *Greenfield Avenue* McCaslin Street to Frank Street Milling: 08/03 Paving: TBD *Euler Way* Meyran Avenue to McKee Place Milling: Complete Paving: 08/04 3AM Work Shift *Meyran Avenue* Forbes Avenue to Fifth Avenue Milling: Complete Paving: 08/04 3AM Work Shift *Niagra Street* Boulevard of the Allies to Craft Avenue Milling: Complete Paving: 08/04 3AM Work Shift *Alternate Streets* The alternate streets below may be added to the current week's schedule in the event of a schedule change. If these alternate streets are not added to the current week's schedule they will be on a weekly schedule in the near future. Please follow us on twitter @PghDOMI <https://twitter.com/pghdomi> for updates. *Forward Avenue* *Beechwood Boulevard* Monitor Street to Guy Street The full 2018 Paving Plan is availible to view as an interactive map here: Burghs Eye <http://pittsburghpa.gov/domi/street-resurfacing/paving-schedule-map.html> Thank you for checking the Department of Mobility and Infrastructure's weekly paving schedule. Check back here, follow us on twitter @PghDOMI <https://twitter.com/pghdomi>, or subscribe to our weekly paving schedule e-mail list: Subscribe <http://eepurl.com/dr6oU9>
participants (1)
-
dave grasso