July 30th - August 4th

This is the City of Pittsburgh's 2018 paving season one week look ahead. This includes the name of the street followed by two cross streets, this section of street in between those two intersections is where resurfacing work will take place. Usually this work will consist of one day of Milling, or removing the existing asphalt, followed soon after by another day of Paving.

Weather and other factors may change the dates listed below.

Please check for posted signs on your street and follow us on twitter @PghDOMI for updates. Street work may be rescheduled to a different day this week or added to a future week's schedule. Please share this information and any updates with your tenants and neighbors.

 

Woodward Avenue
Stetson Street to Dead End
Milling: 07/30
Paving: TBD

South Twenty Fourth Street
East Carson Street to Sarah Street
Milling: Complete
Paving: 07/30

Larkins Way
South Eighteenth Street to South Seventeenth Street
Milling: Complete
Paving: 07/30

Harcum Way
South Seventeenth Street to South Twentieth Street
Milling: Complete
Paving: 07/30

Clinton Street
South Fifteenth Street to Dead End
Milling: Complete
Paving: 07/30

Tyndall Street
Lanpark Street to Allendale Street
Milling: Complete
Paving: 07/30

Universal Street
Tyndall Street to Chetopa Street
Milling: Complete
Paving: 07/30

Newcomer Street (Vidette)
Mutual Street to Kelvin Street
Milling: Complete
Paving: 07/30

Kelvin Street
Newcomer Street to Tybee Street
Milling: Complete
Paving: 07/30

Fire Way
Dead End to Dead End
Milling: Complete
Paving: 07/30

Walton Avenue
Overview Street to Midwood Avenue
Milling: 07/31
Paving: TBD

Well Street
Plymouth Street to Sweetbriar Street
Milling: 07/31
Paving:

Mount Joseph Street
Thielman Avenue Newett Street
Milling: 07/31
Paving:

Brushton Avenue
Baxter Street to Hamilton Avenue
Milling: Completed
Paving: 07/31

Bower Street
Hyatt Street to Pointview Street
Milling: Completed
Paving: 07/31

Fire Way
Dead End to Dead End
Milling: Complete
Paving: 07/31

Universal Street
Tyndall Street to Chetopa Street
Milling: Complete
Paving: 07/31

Tyndall Street
Lanpark Street to Allendale Street
Milling: Complete
Paving: 07/31

Ashtola Way
Allendale Street to Dead End
Milling: Complete
Paving: 07/31

Tyndall Street
Lanpark Street to Allendale Street
Milling: Complete
Paving: 07/31

Stafford Street
Minton Street to Hammond Street
Milling: Complete
Paving: 07/31

Federal Street
Lafayette Street to Perrysville Avenue
Milling: 08/01
Paving: 08/02

Brim Way
Reddour Street to Arch Street
Milling: 08/01
Paving: 08/02

Mulberry Way
Nineteenth Street to Twenty First Street
Milling: 08/01
Paving: 08/02

Spring Street
Devlin Street to Dengler Street
Milling: Complete
Paving: 08/01

Syrian Street
Spring Street to Azul Street
Milling: Complete
Paving: 08/01

Parkwood Road
Eisel Street to 920 Address
Milling: Complete
Paving: 08/01

Moyer Street
Allendale Street to Francisco Street
Milling: Complete
Paving: 08/01

Bergman Street
Hammond Street to Narcissus Ave
Milling: Complete
Paving: 08/01

Wittman Street
Westchester Street to Winona Street
Milling: Complete
Paving: 08/01

Centre Ave
North Craig Street to South Aiken Avenue
Milling: Complete
Paving: 08/02-03

North Neville Avenue
Centre Avenue to Fifth Avenue
Milling: Complete
Paving: 08/02-03

Springfield Street
Crest Way to New York Street
Milling: Complete
Paving: 08/02

Hestor Drive
Hamburg Street to Springfield Street
Milling: Complete
Paving: 08/02

Crest Way
Springfield Street to Dead End
Milling: Complete
Paving: 08/02

Greenfield Avenue
McCaslin Street to Frank Street
Milling: 08/03
Paving: TBD

Euler Way
Meyran Avenue to McKee Place
Milling: Complete
Paving: 08/04 3AM Work Shift

Meyran Avenue
Forbes Avenue to Fifth Avenue
Milling: Complete
Paving: 08/04 3AM Work Shift

Niagra Street
Boulevard of the Allies to Craft Avenue
Milling: Complete
Paving: 08/04 3AM Work Shift

 

Alternate Streets

The alternate streets below may be added to the current week's schedule in the event of a schedule change. If these alternate streets are not added to the current week's schedule they will be on a weekly schedule in the near future. Please follow us on twitter @PghDOMI for updates.

 

Forward Avenue

Beechwood Boulevard
Monitor Street to Guy Street

 

The full 2018 Paving Plan is availible to view as an interactive map here: Burghs Eye

Thank you for checking the Department of Mobility and Infrastructure's weekly paving schedule. Check back here, follow us on twitter @PghDOMI, or subscribe to our weekly paving schedule e-mail list: Subscribe