DOMI Weekly Paving Schedule

 

April 30th - May 4th

This is the City of Pittsburgh's 2018 paving season one week look ahead. This includes the name of the street followed by two cross streets, this section of street in between those two intersections is where resurfacing work will take place. Usually this work will consist of one day of Milling, or removing the existing asphalt, followed soon after by another day of Paving.

Weather and other factors may change the dates listed below.

Please check for posted signs on your street and follow us on twitter @PghDOMI for updates. Street work may be rescheduled to a different day this week or added to a future week's schedule. Please share this information and any updates with your tenants and neighbors.

 

5th Avenue
Shady Avenue to Wilkens Avenue
Milling: 04/28 Night Work 5 PM
Paving: 04/29

 

Frankstown Avenue
Paulson Avenue to East Liberty Boulevard
Milling: 04/30
Paving: 04/30 – 05/01

 

Frankstown Avenue
Washington Boulevard to Lincoln Avenue
Milling: 04/30
Paving: 05/01

 

Frankstown Avenue
Lincoln Ave to East Liberty Boulevard
Milling: 04/30
Paving: 05/01

 

Liberty Avenue
27th street to Ewing Street
Milling: 05/01 – 02 Night Work 7pm
Paving: 05/02 Night Work 7pm

 

East Liberty Boulevard
Frankstown Avenue to Negley Run Boulevard
Milling: Complete
Paving: 04/30

 

North Bellefield Avenue
Bayard Street to Centre Avenue
Milling: Complete
Paving: 04/30

 

Claybourne Street
South Aiken Avenue to South Graham Street
Milling: Complete
Paving: 04/30

 

Greenbriar Way
Elwood Street to Alder Street
Milling: Complete
Paving: 05/01

 

Forbes Avenue
South Braddock Avenue to East End Avenue
Milling: Complete
Paving: 05/02

 

North Bellefield Avenue
Bayard Street to Centre Avenue
Milling: Complete
Paving: 05/02

 

Squirrel Hill Avenue
Fair Oaks Street to North Umberland Street
Milling: Complete
Paving: 05/03

 

Darlington Road
Wightman Street to East Circuit Road
Milling: Complete
Paving: 05/03

 

Alternate Streets

The alternate streets below may be added to the current week's schedule in the event of a schedule change. If these alternate streets are not added to the current week's schedule they will be on a weekly schedule in the near future. Please follow us on twitter @PghDOMI for updates.

 

Howe Street
Hailman Street to Denniston Street
Milling: Alternate

 

South Highland Avenue
Howe Street to Walnut Street
Milling: Alternate

 

Hastings Street
Shady Avenue to Tinsley Way
Milling: Alternate

 

Keith Way
Wilkins Avenue to Dead end
Milling: Alternate

 

Stanton Avenue
North Highland Avenue to Chislett Street
Milling: Alternate

 

Stanton Avenue
Morningside Avenue to Stanton Court
Milling: Alternate

 

Harcum Way
South 17th Street South 20th Street
Paving: Alternate

 

Larkins Way
South 18th Street to South 17th Street
Paving: Alternate

 

Larkins Way
South 26th Street to South 25th Street
Paving: Alternate

 

The full 2018 Paving Plan is avialable to view as an interactive map here: Burghs Eye

Thank you for checking the Department of Mobility and Infrastructure's weekly paving schedule. Check back here, follow us on twitter @PghDOMI, or subscribe to our weekly paving schedule e-mail list: Subscribe