DOMI Weekly Paving Schedule
August 27th - August 31st
This is the City of Pittsburgh's 2018 paving season one week look ahead. This includes the name of the street followed by two cross streets, this section of street in between those two intersections is where resurfacing work will take place. Usually this work will consist of one day of Milling, or removing the existing asphalt, followed soon after by another day of Paving.
Weather and other factors may change the dates listed below.
Please check for posted signs on your street and follow us on twitter @PghDOMI for updates. Street work may be rescheduled to a different day this week or added to a future week's schedule. Please share this information and any updates with your tenants and neighbors.
Tesla Street
Kilbourne Street to Harlem Street
Milling: 08/27
Paving: 08/28
Felix Way
College Street to Sphar Street
Milling: 08/27
Paving: 08/29
Allendale Circle
Francisco Street to Allendale Street
Milling: Complete
Paving: 08/27-28
Allendale Street
Chartiers Avenue to Tyndall Street
Milling: Complete
Paving: 08/27-28
Grimes Avenue
Rochelle Street to Mathews Avenue
Milling: Complete
Paving: 08/27
Zelda Way
Bernd Street to Beltzhoover Avenue
Milling: Complete
Paving: 08/27
Well Street
Plymouth Street to Sweetbriar Street
Milling: Complete
Paving: 08/27
Mahon Street
Chauncey Street to Soho Street
Milling: 08/27
Paving: 08/29-30
Chauncey Street
Wylie Avenue to Bloomer Way
Milling: 08/27
Paving: 08/29-30
Queenston Street
Dartmore Street to Yale Drive
Milling: 08/29
Paving: 08/30
Kearns Avenue
Barbara Way to Warriors Road
Milling: 08/29
Paving: 08/31
Ingomar Street
Vodeli Street to Dead End
Milling: 08/29
Paving: 08/31
Ava Way
Gallion Avenue to Oleatha Way
Milling: 08/29
Paving: 08/31
Gloster Street
300ft Around Greenspace
Milling: 08/29
Paving: 08/31
Roma Way
300ft Around Greenspace
Milling: 08/29
Paving: 08/31
Frank Street
Greenfield Avenue to Hazelwood Avenue
Milling: 08/30
Paving: TBD
Raymond Street
Windermere Drive to Nevada Street
Milling: 08/30
Paving: TBD
Cherokee Street
Ossipee Street to Lyon Street
Milling: 08/30
Paving: TBD
Alternate Streets
The alternate streets below may be added to the current week's schedule in the event of a schedule change. If these alternate streets are not added to the current week's schedule they will be on a weekly schedule in the near future. Please follow us on twitter @PghDOMI for updates.
No Alternate Streets This Week
The full 2018 Paving Plan is availible to view as an interactive map here: Burghs Eye
Thank you for checking the Department of Mobility and Infrastructure's weekly paving schedule. Check back here, follow us on twitter @PghDOMI, or subscribe to our weekly paving schedule e-mail list: Subscribe