This is the City of Pittsburgh's 2018 paving season one week look ahead. This includes the name of the street followed by two cross streets, this section of street in between those two intersections is where resurfacing work will take place. Usually this work will consist of one day of Milling, or removing the existing asphalt, followed soon after by another day of Paving.
Weather and other factors may change the dates listed below.
Please check for posted signs on your street and follow us on twitter @PghDOMI for updates. Street work may be rescheduled to a different day this week or added to a future week's schedule. Please share this information and any updates with your tenants and neighbors.
Boggs Avenue
Wyoming Street to Arion Street
Milling: Completed
Paving: 06/18
Carrick Avenue
Brownsville Road and Eiler Avenue
Milling: Completed
Paving: 06/18
Alverado Avenue
Bayonne Avenue and Dead End
Milling: 06/18
Paving: TBD
Coast Avenue
Rutherford Avenue to Methyl Street
Milling: 06/18
Paving: TBD
Ingomar Street
Vodeli Street to Dead End
Milling: 06/18
Paving: TBD
Plateau Street
Newett Street to Riota Way
Milling: 06/18
Paving: TBD
Rehman Street
Scout Avenue to Hornaday Road
Milling: 06/18
Paving: TBD
Scout Avenue
Rehman Streetto Revision Way
Milling: 06/18
Paving: TBD
Jacob Street
Brookline to Whited Street
Milling: Completed
Paving: 06/19
Elwyn Avenue
Fernland Way to Dead End
Milling: Completed
Paving: 06/19
Isham Way
Stebbins Avenue to Crocus Way
Milling: Completed
Paving: 06/19
Aaron Avenue
Bernard Street to Braid Way
Milling: Completed
Paving: 06/19
Callio Street
Fiat Street to Dead End
Milling: Completed
Paving: 06/19
Lacona Street
Transverse Ave to Dead End
Milling: 06/19
Paving: TBD
Vida Way
Stewart Avenue to Newburn Way
Milling: Completed
Paving: 06/19
Northern Way
Transverse Avenue to Dead End
Milling: Completed
Paving: 06/19
Waterman Avenue
Kirk Avenue to Hopeland Street
Milling: 06/19
Paving: 06/20 - 21
Hestor Drive
Hamburg Street to Springfield Street
Milling: Completed
Paving: 06/19
Ridgemont Drive
Greentree Road to Springfield Street
Milling: Completed
Paving: 06/19
Springfield Street
Crest Way to New York Street
Milling: Completed
Paving: 06/19
Hazeldell Street
Duffland Street to Madeline Street
Milling: Completed
Paving: 06/20 - 21
Hopeland Street
Waterman Avenue to Becks Run Road
Milling: Completed
Paving: 06/20 - 21
Kirk Avenue
Custer Avenue to City Limit
Milling: Completed
Paving: 06/20 - 21
Mount Joseph Street
Theilman Avenue to Newett Street
Milling: 06/20
Paving: TBD
Newburn Avenue
Bethesda Street to Vida Way
Milling: 06/20
Paving: TBD
Strawberry Way
Milling: 06/20 Night Shift
Paving: 06/20 Night Shift
Garland Way
Milling: 06/20 Night Shift
Paving: 06/20 Night Shift
Centre Avenue
Milling: 06/20 Night Shift
Paving: 06/20 Night Shift
McKinley Street
Alice Street to Brownsville Road
Milling: 06/21
Paving: TBD
Tarragonna Street
Alice Street to Daytona Street
Milling: 06/21
Paving: TBD
Alice Street
Georgia Avenue to McKinley Street
Milling: 06/21
Paving: TBD
Desoto Street
Fifth Avenue to Terrace Street
Milling: 06/21 Night Shift
Paving: 06/21 Night Shift
O Hara Street
De Soto Street to Parkman Avenue
Milling: 06/21 Night Shift
Paving: 06/21 Night Shift
Estella Avenue
Climax Street to Chalfont Street
Milling: Completed
Paving: 06/22 - 23
Arlington Avenue
Frederick Street to Spring Street
Milling: Completed
Paving: 06/22 - 23
Saint Joseph Street
Ottillia Street to Ormsby Street
Milling: 06/22
Paving: TBD
Bigelow Boulevard
Parkman Avenue to Bayard Street
Milling: 06/22 Night Shift
Paving: 06/22 Night Shift
The alternate streets below may be added to the current week's schedule in the event of a schedule change. If these alternate streets are not added to the current week's schedule they will be on a weekly schedule in the near future. Please follow us on twitter @PghDOMI for updates.
Caus Way
Rectenwald Street to Ottillia Street
Mcmanus Street
Ottillia Street to Rectenwald Street
Ottillia Street
Saint Joseph Street to Cathedral Avenue
The full 2018 Paving Plan is avialable to view as an interactive map here: Burghs Eye
Thank you for checking the Department of Mobility and Infrastructure's weekly paving schedule. Check back here, follow us on twitter @PghDOMI, or subscribe to our weekly paving schedule e-mail list: Subscribe