PWSA PAVING SCHEDULE
November 2nd – November 6th, 2015
Pittsburgh, PA - The Pittsburgh Water and Sewer Authority (PWSA) contractors are scheduled to complete surface restoration, which includes paving and concrete work for
the week of November 2, 2015. Many work locations will require restricted parking while work is being performed. Signs will be posted in advance and removed as soon as possible.
*Please note that the schedule is weather dependent and subject to change.
Work locations are as follows:
Penn Avenue at Ligonier Street
40th Street at Penn Avenue
126 Maple Terrace
39th Street at Penn Avenue
Boggs Avenue at Wyoming Street
Boggs Avenue at Soffel Street
219 Grant Avenue
749 Stanton Avenue
309 Lincoln Avenue
34 Bismark Street
Forbes Avenue at Moultrie Street
1918 Shamokin Street
813 Spring Garden Avenue
837 Vista Street
1004 Cedar Avenue
7012 Willard Street at Lloyd Street
North Lexington Street at Thomas Boulevard
16 Darlington Court
*Any customer who needs additional information should call PWSA Emergency Dispatch 24/7 at 412.255.2423.
![]()